❗ Compliance monitoring tool — surfaces apparent breaches of the Procurement Act 2023's publication deadlines

▮FTS Explorer ⚑ Late Publication Tracker

Late publication of contract details (UK7) notices under the Procurement Act 2023 — the 30-day deadline in s.53(1)(b) (120 days for light touch contracts). Find a Tender / OCDS data, OGL v3.0.

0 notices 0 authorities 0 suppliers
Loading the full period since the Act went live\u2026
Source: fts-harvester pre-harvested KV store (GET /api/releases?from=&to=) — data is refreshed on a schedule rather than fetched live from FTS on every search. Every filter below runs locally on the harvested data, and everything you can see, you can export.
Measurement options

A framework's lots repeat the same figure, so they are never summed. Choose whether to take the framework's total from the tender notice, or the figure stated against one lot on the contract details notice. This changes values and can move notices across a threshold, so it is kept apart from the filters and is not reset by clear all.

Filter results

clear all
Show:
LT = light touch contract — 120-day publication allowance applies instead of the standard 30 days.

No results yet — press Search.

No results yet.

Split by threshold — different statutory standards apply

Above-threshold notices are subject to the fixed 30/120-day duty in s.53(1). Regulated below-threshold notices follow the softer "as soon as reasonably practicable" standard in s.87 instead — so a below-threshold notice flagged late here may still be defensible under its own, less strict rule. Every figure in this block is counted from the notices actually assessed; none of it is derived by subtraction.

Late notices by month

Based on the date each notice was published, every month since the Procurement Act 2023 went live (24 February 2025). Watch for whether recent months are trending up or down.

How late? (days beyond the allowance)

Distribution of how far past the 30-day (or 120-day, light touch) deadline late notices are — a single "late" figure hides whether that is typically a few days or several months.

Most late notices, by organisation

Top organisations by count of late notices in the current results. Full detail on the Contracting authorities tab.

Late notices by procurement method

Which award routes account for the most late publication, and — in each label — what share of that method's own notices are late. A big slice can just mean a method is used more often overall; the per-method rate in the legend is what indicates whether it is disproportionately problematic.

0late notices
30days, standard contracts
or
120days, light touch contracts
from the day the contract is entered into, to publication of the contract details notice
(s.53(1), Procurement Act 2023)

The publication duty — section 53

Section 53(1) of the Procurement Act 2023 requires a contracting authority that has entered into a public contract to publish a contract details notice confirming this and setting out key details of the contract — within 30 days of that date, or within 120 days if it's a light touch contract.

Procurement Act 2023, s.53(1): a contract details notice must be published before the end of 120 days (light touch contracts) or 30 days (all other contracts) beginning with the day the contract is entered into. In force from 24 February 2025 (S.I. 2024/716).
What counts as "entered into"? Neither the Act nor the Regulations define this precisely. Cabinet Office guidance describes it as the point a legally binding contract takes effect — offer, acceptance, consideration and intent to be bound — which it expects will usually be the signature date, but notes it could instead be tied to a later trigger event or the start of services, depending on the circumstances. This tool always uses the signed date recorded in the notice's own data. If an authority's real "entered into" date genuinely differs from its signature date, this tool's day-count would be affected by that difference, not by anything within the tool's control.

What the notice has to contain

Content requirements differ by award route, set out across four separate provisions of the Procurement Regulations 2024 (SI 2024/692): open or competitive flexible procedure (regulation 32), frameworks (regulation 33), call-off contracts awarded under a framework (regulation 34), and direct award (regulation 35). This tool doesn't distinguish between these routes — every UK7 notice is assessed against the same 30/120-day rule, which is correct since s.53(1)'s timing duty applies uniformly regardless of award route.

Above and below threshold — two different standards

The fixed 30/120-day deadline in s.53 binds above-threshold contracts. A regulated below-threshold contract follows section 87 instead: the notice must be published "as soon as reasonably practicable", with no fixed deadline. So a below-threshold notice showing a long delay may still be defensible under the softer standard that actually applies to it. The two populations are never totalled into a single compliance rate.

This tool does attempt the threshold test, against the Schedule 1 amounts, VAT-inclusive per s.123. From 1 January 2026 Schedule 1 carries two columns: contracts regulated by the Welsh Ministers keep the 2025 figures, everything else moves to the amounts set by SI 2025/1200. Works contracts carry the same figure whatever the authority type, so authority classification is skipped for them. The switch is keyed to when the procurement commenced, not when the contract was signed — SI 2025/1200 reg 3 disapplies the new figures to any procurement commenced before 1 January 2026.

Limitation — when the threshold can't be determined The test needs three things: a stated contract value, the contract type, and either the authority type or a works classification. Find a Tender frequently leaves at least one of them empty, and the commencement date needed to pick the right Schedule 1 column is often absent too. Where any of them is missing the notice is banded "unable to determine" rather than guessed into a band. That count is reported openly on the Dashboard: if it is large, the above/below split below it is describing only the part of the population that could be classified, not the whole.

A separate, later deadline — publishing the contract itself

Contracts worth more than £5 million carry an additional duty under section 53(3): the contracting authority must also publish a copy of the contract, usually as an attachment to the contract details notice. This has its own, later deadline — 90 days, or 180 days for light touch contracts — not the 30/120 days that applies to the notice itself.

Out of scope for this tool This tool tracks only whether the contract details notice itself was published on time. It does not check whether a required contract copy was published, or whether it met its own separate deadline — that is the Contract Publication Tracker's job, against the s.53(3) duty.

Contract award notices are also out of scope

A UK6 contract award notice carries no "publish within N days" duty at all. Section 50 requires it to be published before the contract is entered into, and section 51 then runs a standstill of eight working days from that publication. A UK6 published after signature is not late — it is out of sequence, and the standstill was impossible. Those are different measurements and this tool does not make them.

How this tool assesses each notice

"Date contract signed" is read from the dateSigned field on the OCDS contract object tied to the UK7 document. "Date notice published" is the release date of the UK7 notice itself. The gap between the two is compared against the 30-day duty, or the 120-day duty where the notice text explicitly identifies the contract as light touch. A notice published on day 30 is on time; day 31 is one day late.

Light touch is read from the notice text only. This tool does not infer light-touch status from CPV codes — a contract that would typically fall under the light touch regime (health or social care, say) but whose text doesn't say so in the title, description, or lot text is assessed against the standard 30-day duty. This is deliberate: it means every "late" flag is defensible against the authority's own published wording, not an algorithm's guess about what category a contract falls into.

The date used is the date the notice was first published. A notice can be edited after publication. When that happens Find a Tender re-issues it under a new notice identifier, and the record it then serves carries the date of the edit. Section 53(1) runs to publication, not to the most recent revision of what was published, so measuring from an edit date reports a breach that did not happen — a notice published on day 12 and corrected on day 32 is not a late notice.

Each notice's first publication date is therefore read from the record itself, taking the earliest of the release date and the publication date stated against the notice document, and versions of the same notice are linked across the whole harvest so that the earliest of them is the one assessed. Where a record shows it has been edited but states no first publication date — because the original version falls outside the harvested window, or because Find a Tender simply does not carry the date — the notice is marked unassessable rather than late. That is deliberate: the edit date is the wrong measurement, and reporting a breach on the strength of the wrong measurement is worse than reporting that the question cannot be answered. The Days late column and the compliance percentages both exclude those notices.

This is the opposite of the Compliance Overview and the notice completeness checkers, which assess a correction on its latest version. Both are right for the question each asks: those tools ask what the record now says, this one asks when it first appeared.

Flags

Late the notice was published more days after the contract's signed date than the applicable allowance permits. The "Days late" column shows the number of days beyond the allowance.
Unassessable the UK7 notice doesn't state a contract-signed date, states no publication date, was published before the date it says the contract was signed, or has been edited without stating when it was first published — so lateness cannot be computed. The first of these is itself worth raising: s.53(2) requires the contract details notice to set out the information needed to assess compliance. Unassessable notices are excluded from the late percentage rather than counted as compliant.
Excluded entirely notices with an apparent data error — a stated signed date before the Act's go-live on 24 February 2025 — are excluded from the population and counted separately, since that pattern reflects a data-quality problem with the notice rather than a genuine publication-timing question.

On time is counted directly, never derived by subtracting late and unassessable from a total. If the three don't reconcile against the population, that is a real gap and it should be visible rather than absorbed by arithmetic.

⚑ What happens if an authority doesn't comply?

The Procurement Review Unit — the body originally set up to oversee compliance with the Act — was wound up on 1 April 2026. Its contracting-authority compliance function now sits with the Procurement Compliance Service (PCS), which remains within the Cabinet Office and covers the full range of contracting authorities: central government, NHS, local government and universities.

⚑ Institutional non-compliance Under Part 10 of the Procurement Act 2023 (sections 108–109), the PCS can investigate a contracting authority's compliance with the Act and issue formal recommendations where appropriate. Its stated focus includes institutional breaches — ones regularly being made, or anticipated to be made, by one particular contracting authority — which is exactly the pattern a sustained run of late contract details notices from the same authority would represent, rather than a single missed deadline.

Findings and recommendations from a PCS investigation may be published on GOV.UK, and a contracting authority can be asked to provide progress reports demonstrating what action it has taken. In practice, most late-publication issues are resolved informally once raised directly with an authority — a PCS referral is a longer, more formal route, generally reserved for a pattern that continues after being raised.

Concerns can be raised directly with the Procurement Compliance Service here: raise a concern about a contracting authority's non-compliance.

Sources

This is an unofficial analysis tool built for civil society monitoring purposes. It is not legal advice, and every figure should be checked against the published notice before being relied on or raised with a contracting authority.